Project Overview

The Coffman Street Mobility Improvements project extends from 1st Avenue to 9th Avenue and will become a world-class and truly multi-modal corridor. It will provide the City with:

  • Robust public transit (local, regional and BRT buses), with a near-term future hub just south of 1st Avenue
  • Strong bicycle connections to and from downtown, including to the critical east/west Greenway and to the vibrant Old Town section of the City
  • Better and wider space for pedestrians, up and down the corridor

Do you want to experience the new downtown Coffman Street corridor?

Check out an interactive StoryMap that showcases the future design and highlights what is being constructed.

Visit the StoryMap
Project Status

Updated: October 21, 2025.

Construction started at the end of June 2024 and is expected to be completed by the end of 2025.

Latest Updates:
      • Construction of the Coffman St. corridor is substantially complete.
      • The designated bike lanes are for bicyclists only. Pedestrians must use the adjacent sidewalks and avoid using lanes marked with bike symbols and signs.
      • Learn more about how to use a protected intersection when you watch the informational video above.
      • There is a new “No Left Turn” sign from northbound Coffman St. into the Post Office parking lot at 201 Coffman St. U-turns are not allowed. Vehicles should access the parking lot from 3rd Ave.
      • De-icer should not be used this winter on the concrete sidewalks that were replaced during this project. Businesses should consider an alternative such as sand.
      • Some final work including landscaping will happen in the spring of 2026 after the winter season.

 

Project Map

The following map illustrates the project corridor and area of focus:

 

A Project Line Map of the proposed Coffman Street Busway

Project Schedule
  • Design Complete – December 2023
  • Bid Advertisement – March 2024
  • Construction Award – April 2024
  • Construction Start – June 2024
  • Construction Period – Anticipated 24 months

Coffman Street Mobility Improvement Project FAQs