Coffman Street Mobility Improvements - City of Longmont Skip to main content
A rendering of the crossing of Coffman St and 9th Avenue as viewed from the south
Project Overview

The Coffman Street Mobility Improvements project extends from 1st Avenue to 9th Avenue and will become a world-class and truly multi-modal corridor. It will provide the City with:

  • Robust public transit (local, regional and BRT buses), with a near-term future hub just south of 1st Avenue
  • Strong bicycle connections to and from downtown, including to the critical east/west Greenway and to the vibrant Old Town section of the City
  • Better and wider space for pedestrians, up and down the corridor

Do you want to experience the new downtown Coffman Street corridor?

Check out an interactive StoryMap that showcases the future  design and highlights what is being constructed.

Visit the StoryMap
Project Status

Updated: Dec. 6, 2024.

Construction started at the end of June 2024 and is expected to be completed in the summer of 2026.

Latest Updates:
  • Northbound Coffman St. is closed between Longs Peak Ave. and 9th Ave.
  • Construction continues on the intersection of Coffman St. and Longs Peak Ave.
    • One lane of through traffic is open.
    • Temporary 4-way stop signs have been installed at the intersection.
    • The stop signs will be removed and a new traffic signal installed when construction is complete.
  • Xcel Energy continues to work on Coffman St. between 5th Ave. and 2nd Ave. Parking is prohibited in the areas under construction.

 

Phase 1 (West Side): June 2024 – November 2024

  • Construction on the west side of Coffman St. between 9th Ave. and 6th Ave. is substantially complete.
  • Some work will continue but it will not affect vehicle or pedestrian traffic on that side of Coffman St.

Phase 1 (East Side): December 2024 – June 2025 (Estimated)

  • Traffic is one-way only in the southbound lane of Coffman St. between 9th Ave. and Longs Peak Ave.
  • Northbound traffic is prohibited on these blocks. Rights turns are prohibited from Longs Peak Ave. and 8th Ave. onto Coffman St.
  • On-street parking is currently prohibited on the east side of Coffman St. between 9th Ave. and Longs Peak Ave.
  • Temporary driveway closures on the east side of Coffman St. will be required. The construction team will notify businesses individually before any closures.
  • The 9th Ave. crosswalk on the east side of Coffman St. is closed. Pedestrians must cross on the west side of Coffman St.
  • Both the southbound and northbound lanes of Coffman St. are currently open south of 6th Avenue. The northbound lane between 6th Ave. and Longs Peak Ave. will close in early January.

Phase 2: February 2025 – June 2026 (Estimated)

  • Construction will move south between 5th Ave. and 2nd Ave. with a similar west to east progression as Phase 1.
  • Parking will be prohibited in the areas under construction.
  • A majority of driveways from Coffman St. will remain open unless a temporary closure has been approved by the property owner.

 

Project Map

The following map illustrates the project corridor and area of focus:

Project Schedule
  • Design Complete – December 2023
  • Bid Advertisement – March 2024
  • Construction Award – April 2024
  • Construction Start – June 2024
  • Construction Period – Anticipated 24 months

Coffman Street Mobility Improvement Project FAQs