Project Overview

The Coffman Street Mobility Improvements project extends from 1st Avenue to 9th Avenue and will become a world-class and truly multi-modal corridor. It will provide the City with:

  • Robust public transit (local, regional and BRT buses), with a near-term future hub just south of 1st Avenue
  • Strong bicycle connections to and from downtown, including to the critical east/west Greenway and to the vibrant Old Town section of the City
  • Better and wider space for pedestrians, up and down the corridor

Do you want to experience the new downtown Coffman Street corridor?

Check out an interactive StoryMap that showcases the future  design and highlights what is being constructed.

Visit the StoryMap
Project Status

Updated: April 24, 2025.

Construction started at the end of June 2024 and is expected to be completed in the summer of 2026.

Latest Updates:
  • Coffman St. between 6th Ave. and 9th Ave. is fully open in both directions.
  • Longs Peak Ave. and 5th Ave. east of Coffman St. are open to through traffic.
  • Construction is continuing on the east side of Coffman St. between 2nd Ave. and 6th Ave.
  • Northbound Coffman St. is closed from 2nd Ave. to 6th Ave. Traffic is one-way only in the southbound lane only in these blocks.
  • Coffman St. is fully closed in both directions between 5th Avenue (just north of The Spoke garage entrance) and 6th Avenue. No through traffic allowed. This block is expected to open at the end of May.
  • The school bus stop in front of 230 Coffman Street has been temporarily moved a half-block north. It is expected to move back to its original location in the middle of May.

 

Phase 2 (East and West Sides): February 2025 – June 2026 (Estimated)

  • On-street parking on the east side of Coffman St. is currently prohibited between 2nd Ave. and 6th Ave. Intermittent closures to on-street parking may occur between 6th Ave. and 9th Ave. to complete landscaping.
  • All public parking lots are open and accessible from southbound Coffman St.
  • Access to The Spoke Parking Garage is fully open.
  • A majority of driveways from Coffman St. will remain open unless a temporary closure has been approved by the property owner.
  • Construction is expected to start in late spring on the west side of Coffman St. between 2nd Ave. and 5th Ave.
Project Map

The following map illustrates the project corridor and area of focus:

 

A Project Line Map of the proposed Coffman Street Busway

Project Schedule
  • Design Complete – December 2023
  • Bid Advertisement – March 2024
  • Construction Award – April 2024
  • Construction Start – June 2024
  • Construction Period – Anticipated 24 months