Pedestrian Bridge Replacement: 9th Avenue and Spring Gulch #1
Project Overview
This project will replace the pedestrian bridge over Spring Gulch #1 on the north side of 9th Avenue, between Martin Street and Lashley Street. The result of this project will improve the experience and safety of those walking or rolling across the bridge.
Project Status
Updated: October 13, 2026
This project is in design and scheduled to begin construction in late 2027. The bridge closed to pedestrian traffic in October 2026 and will remain closed for the duration of construction. Long-term pedestrian access to the north side of 9th Avenue will be installed in early November 2026. Until then, pedestrians are encouraged to use the following detour routes:
- Pedestrians heading west, should cross 9th Avenue at the mid-block crossing to continue travelling west on the south side of 9th Avenue.
- Pedestrians heading east, should cross to the south side of 9th Avenue at the Collyer Street intersection.
- The north and south access to the Spring Gulch #1 trail will remain open.
Project Schedule
- Closure of the pedestrian bridge: October 2026
- Long-term pedestrian detour installed: November 2026
- Proposed construction start: Late 2027