Railroad Quiet Zones: Project Group 2
Project Group 2 for the railroad Quiet Zones project includes safety improvements to the five crossings listed below. Construction is anticipated to start in late summer 2026 and is anticipated to be completed early next year. It will include installation of asphalt pavement, concrete curb/gutter/sidewalk, raised medians, pavement markings, signage, fencing and installation of railroad gates with flashers. Two of the crossings listed below will be permanently closed to vehicles, bikes and pedestrians.
Safety Improvements
-
- 4thAvenue/Atwood Street: Four-quadrant gate
- 5th Avenue/Atwood Street: Permanent closure
- 6th Avenue/Atwood Street: Four-quadrant gate
- 21st Avenue: Two-quadrant gate with median
- Terry Street: Permanent closure
Project Status
Updated: November 6, 2026
Note: Trains will remain active on the railroad tracks during construction.
4th Ave./Atwood St.
-
- Construction at the northwest corner of 4th Ave. and Atwood St. is scheduled to begin Nov. 12 and take approximately one week to compete.
- During this time, the southbound lane on the west side of the railroad tracks between 4th Ave. and 5th Ave. will temporarily change to two-way traffic for local access only.
- Residents on the west side of Atwood Street must enter and exit from 5th Avenue with the assistance of flaggers. Access to 4th Avenue will not be available.
- The northbound lane on the east side of the railroad tracks will remain one-way, with no changes to traffic or property access.
- No on-street parking will be allowed on the west side of Atwood Street.
- The northwest corner sidewalks and curb ramps at 4th Avenue will be closed. Pedestrians and bicyclists must use 3rd or 5th Avenues to cross the tracks.
- 4th Ave. will remain open to vehicles with one lane in each direction.
- A short-term full closure of 4th Ave. across the railroad tracks is expected in December.
6th Ave./Atwood St.
-
- Construction at the northwest corner of 6th Ave. and Atwood St. is scheduled to begin Nov. 12 and take approximately one week to compete.
- During this time, the southbound lane on the west side of the railroad tracks between 6th Ave. and Longs Peak Ave. will be closed.
- Drivers may detour using Collyer St. or Baker St.
- The northbound lane on the east side of the railroad tracks will remain one-way, with no changes to traffic or school access.
- No on-street parking will be allowed on the west side of Atwood Street.
- The northwest corner sidewalks and curb ramps at 6th Avenue will be closed. Pedestrians and bicyclists must use 6th or Longs Peak Avenues to cross the tracks.
- 6th Ave. will remain open to vehicles with one lane in each direction.
- A short-term full closure of 6th Ave. across the railroad tracks is expected in December.
5th Ave./Atwood St.
-
- Construction at 5th Ave. will begin after work at the 4th Ave. and 6th Ave. crossings is complete (anticipated early December).
- When construction begins, the 5th Ave. railroad crossing will permanently close to vehicles, bicyclists and pedestrians. There will be no through traffic allowed on 5th Ave. across the railroad tracks.
- All east-west traffic will use 4th Ave. or 6th Ave.
21st Ave.
-
- The crossing will be closed through approximately November 18. Drivers will detour to Collyer Street, 17th Avenue and Alpine Street. There is no outlet from the entrance to the Villas at Park Crest. Motorists should follow designated detour routes and not try to go through the complex.
- Pedestrian access is closed on the north side of 21st Ave. across the tracks. Pedestrians and bicyclists should use designated crosswalks to cross to the south side of 21st Ave.
Terry St./1st Ave.
-
- The crossing is now permanently closed. Trains will continue to sound their horns until BNSF has removed the crossing surface.
- Access to Terry St. is from Coffman St. between 1st Ave. and 2nd Ave.
Construction hours: Monday through Friday from 7 am to 5 pm, with some weekend work as needed.
Construction Schedule
-
- Construction is expected to begin in late summer 2026.
- Some crossings may have overlapping construction schedules.
- The 5th Avenue/Atwood Street crossing will remain open until the 4th Avenue and 6th Avenue crossings are completed.
Quiet Zone Designation Schedule
Once construction of these and adjacent crossing is completed, a request will be filed with the Federal Railroad Administration to implement the Quiet Zone. If approved, the Quiet Zone will go into effect. The City currently anticipates the following schedule for routine train horns to stop sounding:
-
- Winter 2026: 5th Avenue (crossing closure), Terry Street (crossing closure)
- Summer 2027: 3rd Avenue, 4th Avenue, 6th Avenue Longs Peak Avenue, 9th Avenue, 21st Avenue
Work Hours
-
- Regular construction hours are Monday – Friday from 7 am – 5 pm.
- Some work may occur until 7 pm and on Saturdays and Sundays, as necessary.
Questions?
For questions or concerns about the Quiet Zones project, please email QuietZones@longmontcolorado.gov or call 720-526-2044. More information about all four of the project groups can be found by visiting the Railroad Quiet Zones in Longmont webpage.