Railroad Quiet Zones: Project Group 1
Project Group 1 for the railroad Quiet Zones project includes the four crossings listed below with the improvements. Construction is anticipated to start in May 2025 and is anticipated to be completed by July 2026. It will include installation of asphalt pavement, concrete curb/gutter/sidewalk, raised medians, pavement markings, signage, fencing and installation of railroad gates with flashers.
Once construction of these and adjacent crossing is completed, a request will be filed with the Federal Railroad Administration to implement the Quiet Zone. If approved, the Quiet Zone will go into effect. See the project FAQs for more information about Quiet Zones and when train horns will stop sounding routinely at designated crossings.
Current Status
Updated Apr. 29, 2026.
3rd Avenue Crossing
- Construction is substantially complete. Minor work on the crossing ages will occur in early June but should not affect traffic.
- All lanes of traffic on 3rd Avenue and Atwood Street are open.
17th Avenue Crossing
- Construction is complete.
- This will be the first crossing submitted to the Federal Rail Administration for Quiet Zones designation. A decision is expected in the fall of 2026. If approved, train horns will no longer sound routinely at this crossing.
9th Avenue Crossing
- Construction is substantially complete. Minor work on the crossing gates will occur in early June but should not affect traffic.
Longs Peak Avenue Crossing
- Construction is complete.
Safety Improvements
- 3rd Avenue/Atwood Street: Four-quadrant gate (quad gate)
- Longs Peak Avenue: Four-quadrant gate (quad gate)
- 9th Avenue: Two-quadrant gate with median
- 17th Avenue: Two-quadrant gate with median
Schedule
- Phase 1 (May 2025 – April 2026): Longs Peak Avenue, 9th Avenue and 17th Avenue
- Phase 2 (March – June 2026): 3rd Avenue
Work Hours
- Regular construction hours are Monday – Friday from 7 am – 5 pm.
- Some work may occur until 7 pm and on Saturdays and Sundays, as necessary.
Questions?
For questions or concerns about the Quiet Zones project, please email QuietZones@longmontcolorado.gov or call 720-526-2044. More information about all four of the project groups can be found by visiting the Railroad Quiet Zones in Longmont webpage.