Price Park Tank Pump Station Testing to Begin November 4 - City of Longmont Skip to main content
Digital rendering of Price Park Tank

Price Park Tank Pump Station Testing to Begin November 4

As part of the Price Park Tank Replacement Project, an 8 million gallon (MG) tank and a 12 million gallon per day (MGD) pump station have been constructed. The larger tank, new pumps and control equipment will improve the ability of the site to deliver water to the entire City to meet current and future needs and provide water service during emergencies.

 

The City plans to begin testing the new equipment on Monday, Nov. 4, 2024 and this will continue through the end of November to early December, 2024. During this time, you may notice discolored water in your home when the pump station is being operated. This is not unsafe but it may be undesirable. If you experience discolored water, please report it to Longmont Customer Service at (303) 651-8416.

 

After the testing is finished, the Price Park Tank Replacement Project which started in September 2022 will be substantially complete. The tank and pump station will transition to regular maintenance and annual testing.

 

For more information, visit our Price Park Tank Replacement webpage. Frequently Asked Questions are toward the bottom of the page or you can contact Longmont Customer Service for more information.