November 20, 2026 – The City of Longmont expects to reopen the 21st Avenue railroad crossing to vehicles and pedestrians at the end of the day Wednesday, Nov. 25, just ahead of the Thanksgiving holiday. The reopening follows several weeks of construction as part of the Railroad Crossing Safety Improvements (Quiet Zones) Project.
Pedestrian Access Closed Nov. 23–25
Pedestrian access across the railroad tracks at 21st Avenue will be completely closed from Monday, Nov. 23, through Wednesday, Nov. 25, while crews complete work needed to reopen the crossing. Pedestrians will not be able to cross the railroad tracks on either side of 21st Avenue during this closure.
Once the crossing reopens, vehicles will be able to travel in both directions on 21st Avenue, and sidewalks on both sides of the road will be open to pedestrians. No additional road closures are anticipated for the Quiet Zones Project at this location.
Some construction activities will continue after the reopening, including installation of fencing, gates and signage. These improvements are part of the safety upgrades required to establish a Quiet Zone at the crossing.
When Will Train Horns Stop at 21st Avenue?
Trains will continue to sound their horns until the Quiet Zone is established. The City expects to submit an application to the Federal Railroad Administration (FRA) in early 2027. Train horns are anticipated to stop sounding routinely at the 21st Avenue crossing in summer 2027, following completion of the federal process.
For the latest construction information, visit the Group 2 Quiet Zones project webpage. Questions or concerns can be directed to the project hotline at 720-526-2044 or QuietZones@longmontcolorado.gov.